Written by: Opinder Liddar

When I started my career as an architect, a planning application would comprise drawings showing the site, the layout of existing buildings, and plans and elevations of the new proposal. This would be accompanied by a planning application form, in which you would make a brief statement about the nature of the proposal, e.g. “a replacement dwelling”.

The application would be submitted, a consultation for comments (generally from immediate neighbours) would be carried out, and I could then converse with the planning officer to negotiate towards a positive decision or make changes to the scheme.

As time went by, Design & Access Statements were introduced, requiring us to demonstrate that we had considered the design in relation to its context and minimised its impact on neighbouring land and buildings. During this stage of the planning application process, we could still speak directly with the planning officer.

I have now moved to today’s situation, where in many local authorities it is no longer possible to speak with the case officer during the consideration of a planning application. Most councils require you to submit a pre-application if you wish to have a preliminary discussion about your proposal; however, pre-application responses are often caveated with “this is the opinion of the officer and does not bind the council to any advice given…” or words to this effect. This can mean that the outcome of a pre-application may not be worth the paper it is written on.

When it comes to submitting a planning application for a new house, whether you have the results of a pre-application or not, you are often required to provide the following additional information:

Topographic survey – to show existing and proposed levels, boundaries, neighbouring buildings, and other pertinent features on the site.

Ecological survey(s) – to prove the existence or non-existence of bats or other protected species on or near your site. If bats are present, this needs to be supplemented with emergence surveys, which can only take place between May and September, and/or hibernation surveys, which can only happen between November and March. If bird species are found, surveys are required which must take place at different times to any bat surveys performed.

Drainage surveys – to show how your proposal will deal with surface water and foul drainage. Nowadays, this requires an assessment of the existing infrastructure and detailed drawings showing the depth of the drains, along with calculations to demonstrate how the drainage of water is managed.

Hydrology Assessment – required if your development is within a potential flood zone. The requirements are more arduous in flood zone 3 than flood zone 2.

Arboricultural assessment – if there are trees on or bounding your site, they need to be identified and accurately plotted onto the drawings to show your development in context to the trees. You also provide an arboricultural report to show (1) how your proposal is justified and (2) the tree protection measures that you will put in place as you build the project.

Construction Method Plan – how site deliveries and parking will be managed during construction.

Structural survey – if you intend to knock down or refurbish an existing structure to create your dream project.

Contamination survey – if you are developing a brownfield site, you need an assessment of any potential risk from previous uses on the site. You may also need geotechnical surveys to assess ground conditions for contaminants.

Landscape Design – plans and schedules of the hard and soft landscaping to form part of your proposal.

Landscape Visual Impact Assessment – if you are planning to build a new home in an Area of Outstanding Natural Beauty or on a visually sensitive site.

Light pollution assessment – raised in connection with developments near the coast or in rural areas, as artificial lighting is thought to impact habitats.

Heritage Assessments – applicable if you want to carry out development that affects Listed Buildings or potentially falls within Conservation Areas.

Highway reports – covering car parking availability and connections to a public road.

Biodiversity Net Gain Matrix – you will need to demonstrate a net gain in biodiversity as a result of the construction of your new house. This would be difficult to prove if you were aiming to build on land that used to be a garden for another property. At present, self-builders are often able to claim an exemption from this; however, you will still need to describe some biodiversity measures that you will implement.

Energy Statements – usually in the form of SAP calculations, followed by commentary on the sustainable measures that form part of the design, to show how you are meeting the local authority’s aim for carbon reduction.

Carbon Assessments – now a requirement in local authority areas that have declared a “Climate Emergency”, particularly where you intend to demolish an existing building. The calculations require you to show the amount of carbon in the existing structure that will be lost, as well as the carbon used in the construction of your new building. This includes the energy used in making, transporting, and building with the materials you want to use, and their impact over the lifetime of the structure until demolition.

Building Regulations Assessments – due to recent changes as a result of the Building Safety Act 2022, you need to carry out regular reviews of your design to demonstrate that it will meet Building Regulations from the concept design stages through to completion.

Post-Occupancy Review – a commitment given upon completion that your ecological and sustainable measures are in place and working.

Tranquillity Assessments – yes, not many people have heard about this one; it is an assessment of well-being factors associated with the development site…

The list goes on, and I find that new requirements appear every year. You will have heard the story of the frog in the kettle that does not notice as the water around it approaches boiling point; well, we have managed to create a planning system that nobody would have intentionally designed in one sitting — one that stifles creativity and development and results in less housing being built.

You can see that, within a relatively short timeframe, the number of specialist reports and surveys required to make a planning application has increased exponentially. This is a very expensive and time-consuming process, with no guarantee of a positive outcome for your investment. Requirements originate from local planning authorities or individual local plans and are therefore not applied equally across the country. This is unfair and perhaps explains how the system has grown unchecked.

Much of this information should not be needed at the planning application stage and should instead be made a condition of a successful application, if relevant. Alternatively, the rules should be rewritten so that a base standard is expected of all development, rather than every project having to prove a different standard depending on where it is located.

Our clients, and most self-builders, are faced with a planning system that expects them to spend tens of thousands of pounds of their own taxed money simply to find out whether their local authority will allow them to develop their land. The system offers no guarantee of approval, yet requires significant and unnecessary expenditure before the outcome is known. If an application is rejected, a substantial proportion of that investment in consultants’ fees and reports is lost.

This has reached a point where many prospective clients are no longer prepared to gamble such significant sums of money, and so projects simply do not happen. You might assume that someone else would make an application in their place and successfully build on that plot, but I am increasingly seeing that this is not the case. I suspect this is part of the reason why the Government is going to miss its housing targets.

I would love to devote more of my time to doing what I do best — designing buildings — but architects are now expected to (1) have expertise across all of these subject areas and (2) manage all of the relevant consultants. In turn, planning officers are expected to have the same breadth of expertise. Often they do not, and so councils employ or hire additional specialists to review the reports. If you cannot satisfy all of these requirements, your scheme could be refused for something as simple as your bat survey being deemed “out of date” (they are valid for two years).

Planning is constantly evolving, and it can quickly become overwhelming. If you have questions about the planning process and need expert advice from architects who deal with this every day, please get in touch, we’ll be happy to help.